Cost Outline for Litchfield Renovation submitted by a Tax Payer

This information was compiled by a concerned citizen. Disclaimer. “I am not an accountant. I am only a local citizen – taxpayer.”

The following information outlines the history and finances of the current Litchfield project. The amounts were calculated from documents obtained through FOIA and other public means.

Superintendent Jeanne Davis announced at the Board Committee Meeting held on July 2, 2012 that she has stopped all work on the project and is now recommending that the project be changed to house two classrooms for the Tazewell-Woodford Head Start Program. This change order will be on the agenda of the July 18th Board Meeting.(See video for her complete announcement).